Early interest in Open Days encourages SuperHome owners to host more events. If you'd like to visit this property please contact the owner and let them know. SuperHomers are often happy to respond to questions about their refurbishment project by email between times. Please read ‘more on contacting this SuperHomer’ before you make contact.
Bertram Street Low Energy Victorian Terrace:
This house was retrofitted with energy efficiency measures to reduce CO2 emissions by 77%. These included a pioneering method of fitting internal wall insulation while the residents continued to live in the property. Sustainable features include vacuum glazing, MVHR, solar thermal and PV.
The property is a 3 storey Victorian (1880s) terrace, located in the Dartmouth Park Conservation area. In 2010 a consortium of Camden Council, the Sustainable Energy Academy, United House and Parity Projects won funding under the Retrofit for the Future competition to upgrade the property to reduce carbon emissions by 80%. The key feature of the upgrade was the technique (known as WHISCERS) of fitting internal wall insulation by using laser wall measurement and off site panel cutting to reduce mess, disruption and work time.
Project Partners
The Sustainable Energy Academy, United House, Parity Projects, Camden Council Housing Unit and the National Energy Foundation. The refurbishment was funded through the Technology Strategy Board’s Retrofit for the Future Programme.
1) The heat demand of the house was reduced by cocooning the house in an envelope of insulation and advanced low energy glazing:
a) Internal wall insulation (100mm in most areas), reducing the U-value from 2.1 to 0.21, installed using the WHISCERS method
b) Vaccuum glazing in sashes, reducing the U-value from 4.5 to 1.8
2) The air flow through the house was controlled by draught stripping all windows, and providing mechanical ventilation and heat recovery in areas of high humidity (kitchen and bathroom)
3) Renewable solar energy was used to supply hot water and electricity (1.1 KWp) – over 1000 KWh of electricity generated in the first year of operation
4) The remaining energy demand was efficiently supplied using an “A” rated condensing boiler
5) Appliances were chosen to reduce electricity demand, and meters provide information and feedback to residents to enable them to reduce their energy consumption further.
Other Camden homes open to the public this September to view: St Augustine’s Road and Belsize Park Gardens
Significant reductions in CO2 emissions and heating costs were achieved by:
1) Reducing heat loss through the building fabric – the walls, roof and windows – and cocooning the house in an envelope of insulation and advanced low energy glazing
2) Using renewable energy to supply hot water and electricity
3) Supplying the remaining energy efficiently
4) Addressing lifestyle choices and looking at how the occupant can make a difference.
The walls of the house are solid brick, and originally up to 40% of the heat lost from the building was lost through these. Because the house is located in a conservation area, external wall insulation was not allowed due to planning constraints. Therefore internal wall insulation was the only realistic option to reduce heat loss through the walls.
Internal wall insulation can be time consuming and disruptive, requiring the occupants to move out of the property while work is being done. The major innovation of this retrofit is in using the WHISCERS process for the internal wall insulation. WHISCERS uses laser measuring to record the shape of the walls, then the information is transferred to an off-site board cutter, the panels are brought to site and erected in typically 1-1.5 hrs per room. The reduced disruption, mess, noise and installation time allowed the residents (a family of five) to remain living in the house throughout the retrofit programme.
100mm of polystyrene was used for internal wall insulation. The results from monitoring for interstitial condensation show that moisture levels are within acceptable limits.
The monitoring at Bertram St was carried out from Jan 2011 – Dec 2012.